           Due  to heavy  snow  fall,  heavy
          winds and avalanches, the pass
          used to normally close by October/
          November and re-open only by April/
          May in the yesteryears with the total
          closure time averaging almost five to
          six months. However, in 2020, due
          to the operational necessity along
          the Northern Borders, BRO was
          given the responsibility to keep the
          pass open till the end of December
          which was done in an efficient
          manner by the organisation, fighting
          against all odds. True to its name,
          BRO not only kept the pass open
          till the end of December but also
          ensured early opening of the pass
          in the month of Feb/Mar. Ever
          since, defying life-threatening odds,
          BRO has been constantly working
          towards truncating the road closure
          period, which till recent past was
          anything up to 150 days. In 2021
          the pass was closed only for 110
          days in winters. In 2022, Zojila Pass
          was kept open till as late as January
          4 and was re- opened in just 73 days,
          a feat hitherto unimaginable. This
          year, the pass remained trafficable
          till as late as Jan 6 2023, thereby
          creating a new historic precedence
          of its kind. BRO Srinagar-Zojila-Leh
          (NH-1) on March 16 for traffic after
          a record closure time of just 68 Days.